Expropriation in Serbia: Compensation, Appeal and Procedure
A guide for owners who have received a summons or a decision on expropriation in Serbia: how to recognise the procedure, check the decision and react in time.

Expropriation in Serbia is only possible in the public interest established on the basis of law and against compensation that may not be lower than the market value. If you have received a summons or a decision, check which act it is, what it covers and what instructions on legal remedies it contains. If a road or infrastructure is already on your plot but you have not received a formal decision, the first step is to distinguish such de facto occupation from formally conducted expropriation.

First establish: is there a decision or is the land already occupied
For the owner, the initial questions are simple but important: have administrative proceedings been initiated, and is there an act that relates specifically to their property? The Serbian Expropriation Act allows the expropriation of land, buildings and other structures when the public interest has been established on the basis of law. It is not enough that public works are being carried out nearby or that someone has verbally announced a project.
Formal expropriation means proceedings before the competent authority and a decision on expropriation. In that situation the owner will usually have a summons from the municipal administration, a notice of the proposal, a decision establishing the public interest or a decision that directly specifies the property and the right being taken away or restricted.
De facto expropriation is the term used when land has actually been put to public use, for example when a road or part of the infrastructure has been built on it, but the owner cannot find a formal decision on expropriation. The mere existence of the works does not answer the question of the legal basis for the occupation in advance. The documentation needs to be compared with the actual situation and the boundaries of the plot.
So check immediately:
- whether you have received a summons from the municipal administration or another written notice;
- whether there is a Government decision establishing the public interest;
- whether a decision on expropriation has been served on you;
- whether an annotation of expropriation has been entered in the cadastre;
- whether the works, fence, road or installations on the ground are on your plot and to what extent.
The property title sheet (list nepokretnosti) and a copy of the cadastral plan are useful for this first check - how the cadastre records ownership is explained in a separate guide. They should then be compared with the cadastral plot number, area and description in the act you have received. Questions of expropriation and the extent of land taken fall within real estate and construction law, particularly when the data in the documentation and the situation on the ground do not match.
Who can be the beneficiary of expropriation
The beneficiary of expropriation is not automatically the Republic of Serbia. Under the Expropriation Act, it may be the Republic, an autonomous province, a city, the City of Belgrade, a municipality, public funds and public enterprises. In certain cases it may also be companies founded by public enterprises, as well as companies with majority state capital.
You should therefore not conclude who the beneficiary in the specific proceedings is from the name of the project or the contractor alone. Check who is named in the decision, the proposal or the summons. This matters because the proceedings are conducted on the proposal of a specific beneficiary, not merely because a project of public importance exists.
How the formal expropriation procedure works
The formal procedure follows an order the owner can track through the documents they receive. First, the Government establishes the public interest by a decision. That decision is published in the Official Gazette, and an administrative dispute may be brought against it within 30 days of service.
Once the public interest has been established, the beneficiary of expropriation files a proposal with the municipal administration in whose territory the property is located. The proposal is filed within one year of the public interest being established. The beneficiary must enclose proof that the funds for compensation have been secured, in the form of a bank guarantee or a confirmation of secured budget funds.
The municipal administration, namely its property-law department, conducts the proceedings. Before issuing a decision it must hear the owner. This is the moment when the owner should point out any data that are incorrect or incomplete: the plot number, the area, the existence of buildings and other circumstances relevant to the extent of the taking.
The beneficiary may request that an annotation of expropriation be entered in the cadastre. If the owner disposes of the property after that annotation, the disposal has no effect against the beneficiary of expropriation. The annotation is therefore not the same as a change of ownership, but it is an important signal that the proceedings have been initiated and that every further step requires a careful check of the acts.
After the proceedings have been conducted, a first-instance decision on expropriation is issued. The decision cannot lawfully be based on a public interest that has not previously been established, because a decision on expropriation issued without a decision on the public interest is null and void.
Special laws may apply to certain large infrastructure projects. So check the name of the regulation the specific decision refers to, and do not rely only on the general rules of the Expropriation Act.
Appeal and administrative dispute
An appeal may be lodged against the first-instance decision on expropriation, and it is decided by the ministry responsible for finance. You must check the deadline in the instructions on legal remedies at the end of your decision. Under the general rules of administrative procedure, the deadline for an appeal is 15 days from service, but the content of the specific act and the regulation applied should be checked before the deadline expires.
The appeal concerns the first-instance decision. Once the decision is final, an administrative dispute may come into consideration. These are different procedural remedies, and it is not wise to let the appeal deadline pass on the assumption that every issue can later be raised in the same way. Review of administrative acts and administrative disputes belong to the field of administrative proceedings and disputes.
The outcome and duration of any legal remedy depend on the content of the act, the course of the proceedings and the facts of the specific case. This article is general information, not legal advice on a particular decision.
What to check in the decision before the deadline for a legal remedy expires
Do not read the decision merely as a notice that works will be carried out. Compare each of its details with the property title sheet, the cadastral plan and the actual situation. In particular, check the cadastral plot number, the area covered, the type of right being taken away or restricted and the name of the beneficiary of expropriation.
Then check whether the description of the taking matches what actually exists on the property. Where relevant to the case, pay attention to the house, flat, business premises, fence, auxiliary and other appurtenant structures, plantations and other parts located on the plot. If only part of the plot is being taken, clearly mark on the plan which part is listed in the decision and which part remains outside it.
Complete expropriation means that ownership of the property changes on the day the decision becomes final and binding. Incomplete expropriation does not necessarily transfer ownership, but may mean the establishment of an easement or a lease of the land for a fixed period. So it is not enough to find only the name of the project in the decision. Check exactly which right is being established and what use of your property it permits.
Failing to lodge an appeal or another available legal remedy can have serious consequences, but these cannot be assessed in advance without reviewing the decision and the facts of the case. This does not mean that any later legal protection is automatically excluded. Even so, the deadline in the instructions on legal remedies should not be ignored.
Be careful with investments as well. As a rule, no compensation is paid for investments made after the written notice of the filed expropriation proposal, except for the necessary costs of using the property. Before major works on a building or plot, check the date and content of the notice you have received.
Complete, incomplete and temporary expropriation
The extent of the taking determines exactly what you lose or have to tolerate on the property. In complete expropriation, ownership is taken away. In incomplete expropriation, an easement may be established, for example a right to use part of the land for a particular purpose, or a lease of the land for a fixed period.
A lease under incomplete expropriation may last no longer than three years. When the lease expires, the land is restored to its original condition. Temporary occupation may also last no longer than three years. In both cases, compare the actual use of the land with the content of the decision: the area used, the purpose of use and the duration should not be left unchecked.
If the decision refers to an easement, temporary occupation or a lease, keep the act, the cadastral plan and photographs of the condition of the plot. These documents help to establish later whether the actual taking stayed within the limits set by the decision.
How much compensation is paid and why there is no price per square metre
There is no single predetermined price per square metre that applies to all expropriated land. Compensation is determined according to the market value of the specific property and the circumstances of the specific case, so the same area can have a different value depending on its purpose, location, characteristics, the extent of the taking and the time of the valuation.
For land, the market value is assessed by the authority responsible for the tax on the transfer of absolute rights, i.e. the Tax Administration. That assessment is an important starting point, but when compensation is disputed it is not necessarily the final answer. The owner should check whether the assessment corresponds to the specific plot and the part covered by the decision, including its area, type of cultivation, access and purpose.
Land cannot be treated in the same way as a house, flat or business premises. For those properties, too, the law starts from the market value, but the valuation must cover what is actually the subject of expropriation. There are special statutory rules for orchards, vineyards and forests, which is why it is important that the documentation clearly shows what is on the land.
Compensation does not always have to be purely monetary. The owner of a flat, house or business premises may, under statutory conditions, request other suitable property. A farmer for whom the land is a source of livelihood may have grounds to request other land, subject to statutory conditions and exceptions. The law also allows compensation higher than the market value when family and financial circumstances are significant for the owner's livelihood.
When the value is assessed
The market value is determined according to the circumstances existing at the time of the compensation agreement. If no agreement is reached, the circumstances at the time of the first-instance decision on compensation are relevant. An earlier valuation, an advertisement or a comparison with another plot therefore does not in itself settle the question of the amount.
Before accepting an offer, check: which cadastral plot and area the valuation covers, whether the type of property is described correctly, whether buildings and plantations are included where they exist, and whether the actual extent of the right being taken away or restricted has been taken into account. How much compensation you are entitled to depends on these data, not only on the number of square metres.
If you disagree with the compensation offered: agreement or basic court
The beneficiary of expropriation must deliver a written offer on the form and amount of compensation within 15 days of the decision becoming final and binding. The offer should be neither accepted nor rejected without comparing it with the decision, the cadastral data and all parts of the property it relates to.
Once the decision becomes final and binding, the municipal administration schedules a hearing to attempt an agreement. If an agreement is reached and entered in the minutes, it has the force of an enforceable document. That is why the owner should check carefully before signing what the agreement covers, the amount or type of compensation and whether all issues covered by the expropriation have been resolved.
If no agreement is reached within two months of the decision becoming final and binding, the municipal administration forwards the case file to the competent basic court to determine compensation. If the administration fails to do so, the owner may apply to the court directly. Before the court, compensation is as a rule determined with an expert assessment. The outcome, the amount of compensation and the duration of the proceedings depend on the facts, the documentation and the findings in the specific case.
The costs of the expropriation proceedings and of determining compensation by agreement are borne by the beneficiary of expropriation. Submissions and decisions in those proceedings are exempt from fees.
When the beneficiary can take possession
The compensation offer and handing over possession of the property are not the same issue. As a general rule, the beneficiary takes possession on the day the decision on compensation becomes final and binding or the compensation agreement is concluded.
The law provides exceptions for earlier handover due to urgency, as well as special rules for energy and linear infrastructure facilities. So if handover is requested before the compensation issue is settled, check which legal basis the authority relies on and what exactly the act you have received orders.
When to request expropriation of the remaining part of the plot
If only part of a plot is taken, the remainder does not necessarily remain usable. The owner may request expropriation of the remaining part if there is no economic interest in using it or if their livelihood is significantly impaired. The authority must inform the owner of this possibility.
The request may be filed no later than two years after the construction or works are completed. In the request, it helps to link the remaining area specifically to the situation on the ground: whether access remains, whether the plot can still be used for its purpose, whether the shape or size of the remainder is functional and how the taking has affected its use. Whether the conditions are met is not presumed in advance, but assessed according to the actual condition of the plot.
Deadlines not to miss
| Procedure or step | Deadline | Counted from | What the owner checks |
|---|---|---|---|
| Administrative dispute against the decision on public interest | 30 days | Service of the decision | Date of receipt and instructions on legal remedies |
| Appeal against the first-instance decision on expropriation | Deadline stated in the instructions on legal remedies, 15 days under the general rules | Service of the decision | The exact deadline and the authority to which the appeal is filed |
| Beneficiary's written offer of compensation | 15 days | The decision on expropriation becoming final and binding | Whether the offer has been delivered and what it covers |
| Agreement on compensation before the case file is sent to court | 2 months | The decision becoming final and binding | Whether an agreement has been reached or the file should be sent to the basic court |
| Request for expropriation of the remaining part | No later than 2 years | Completion of the construction or works | Whether the rest of the plot is actually usable |
| Request for annulment of the decision because significant works were not carried out | After 3 years, but not after 5 years | Three years from the decision on compensation or the agreement becoming final, with an outer limit of five years | Whether significant works have been carried out and whether the outer deadline is still running |
The former owner or their heir may request annulment of the decision if the beneficiary has not carried out significant works within three years of the decision on compensation becoming final and binding or the agreement being concluded. Such a request cannot be filed after five years have passed. Always check the deadlines against the specific act and the regulation it refers to, because special rules may apply to certain infrastructure projects.
If a road or infrastructure is already on private land without a decision
If a road, installation or public area has already been built on the land and you have not found a decision on expropriation, do not immediately draw conclusions about the legal nature of the situation. The actual occupation needs to be compared with the cadastral records and the documentation issued by the competent authorities or created during the works.
Keep the property title sheet and the cadastral plan, the contract or other document by which you acquired the property, all correspondence and notices from authorities or contractors, and dated photographs. Evidence of the condition before the works, available documentation on the works carried out and surveying data or a survey report from which the occupied area can be determined may all be important.
If there are buildings or plantations, or the use of the remaining part of the plot has become more difficult, keep the documentation that shows this as well. The legal basis, the actual extent and any claim for compensation are assessed on the basis of the specific facts and evidence, not merely because the work on the ground is visible.
If there is a decision, the next step is to check its scope, the instructions on legal remedies and the deadlines. If there is no decision or you cannot find it, keep the documentation on the occupation and the earlier condition of the property. This article is general information; the assessment of legal remedies, compensation and deadlines depends on the specific act and the circumstances of the case.
Frequently asked questions
What is expropriation and when can the state or a public beneficiary claim property?
Expropriation is the taking away or restriction of rights to property in order to achieve a public interest, against compensation. It cannot be based merely on the fact that the land is suitable for a road, installations or another public project. The procedure is conducted under the Expropriation Act, and the public interest must be established for the specific project. The beneficiary of expropriation then initiates proceedings before the competent administrative authority where the property is located. The owner should check which cadastral plot is covered, whether complete or partial taking is requested and whether buildings, plantations and other appurtenant parts are correctly listed. The content of the decision and the available protection depend on the specific proceedings and documentation.
How do I find out whether formal proceedings have been initiated for my plot or whether it is de facto expropriation?
If you have received a summons, notice or decision from the competent authority relating to expropriation, formal proceedings most likely exist. Keep every document and check the plot number, the extent of the taking, the details of the beneficiary of expropriation and the instructions on legal remedies. If there is already a road, pipeline, power line, public area or other works on the land, but you have never received a decision and the right has not been regulated by contract, it may be de facto occupation of the land. The mere fact that works have been carried out does not answer the question of your rights or the amount of any compensation. The actual situation, the cadastral data, the basis on which the land is used and all available documentation need to be established.
Is there a predetermined price per square metre for expropriated land?
There is no single predetermined price per square metre that would apply to every expropriated plot. Compensation is assessed according to the circumstances of the specific property and proceedings, so its type, area, location, purpose, status in the records and other characteristics that may affect value all matter. The price of land in another location therefore cannot automatically be applied to your plot. In a partial taking, it is also important to consider what remains with the owner, including access, shape and the possibility of using the remaining part. For a building, plantation or other elements on the land, it is also relevant whether they are covered by the proceedings. An assessment requires a review of the specific acts and facts.
What happens if I disagree with the compensation offered?
Disagreeing with the compensation offered does not mean you have to accept the offer without checking it, but nor does it mean that every objection will lead to a different amount. First, carefully compare the offer with the data on the plot, the extent of the expropriation and what is actually on the property. The Expropriation Act provides for a procedure to determine compensation by agreement, and if no agreement is reached, compensation may be decided by a court in non-contentious proceedings. In that situation, evidence of the property's characteristics and an expert assessment may be important. Do not sign a statement whose consequences are unclear. The deadlines and next steps depend on the act you have received and the stage of the proceedings.
Can I request that the remaining part of the plot also be expropriated if I can no longer use it economically?
You can raise the question of the plot being taken in full when only part of it is expropriated and the remaining part no longer serves an economic purpose for you as a result. This is not presumed automatically just because the plot has become smaller or irregularly shaped. You need to show how the partial expropriation affects the actual use of the remainder, for example access, the possibility of cultivation, construction or use for its purpose. The request and evidence should be submitted in time in the proceedings, because the content of the decision and missed legal remedies may be significant. A cadastral plan, photographs, data on access and documentation on the purpose of the land are useful. Whether the conditions are met is assessed according to the actual condition of the plot.
Which documents should I keep if a road, infrastructure or public area has already been built on private land without a decision?
Keep proof of your right to the land, an extract or property title sheet, the cadastral plan, the purchase contract or other valid document on the basis of which you acquired the property. Also gather photographs and recordings of the existing situation, showing the position of the road, line or public area in relation to the plot, as well as correspondence with authorities, public enterprises or contractors if you have any. Construction and planning documentation, surveying data, earlier decisions and evidence of when the works were carried out may be important. Do not change the situation on the ground in order to gather evidence. It needs to be established who uses the land, on what legal basis and which part of the plot is affected. A lawyer can review the documents and assess the next legal step.

If this is your matter, the first step is a conversation.
SCHEDULE A CONSULTATION